Following the Audit Service Sierra Leone (ASSL) 2014 Report which uncovered massive discrepancies at all the various MDAs, it was discovered that at the Works Ministry, procurement procedures were not used for procuring works, goods and services.

Pres-Ernest-Bai-Koroma

However, it was observed that the Ministry did not follow procurement procedures in awarding contracts for consultancy services for the design, tender and full supervision of construction works for a new ministerial building.

A contract for feasibility studies of eight trunk roads which totaled Le4,773,912,000 had no request and solicitation from the ministry or expressions of interest from bidders.

ALSO READ: Ministers Of Works ‘Dodging’ Parliament After His Corrupt Deeds Are Exposed

In addition, even though the procurement officer and the internal auditor recommended that the Ministry should liaise with SLRA for the award of contracts for the construction of trunk roads, the Ministry did not follow their recommendations.

There were also no minutes of procurement committee meetings and approvals by the committee.

Furthermore, the audit team observed that the professional wing of the Ministry had done a similar design for the new Ministerial Building for which the contract had been awarded.

ALSO READ: Meet Francis Tucker, Sierra Leonean Who Is Constructing The First Helicopter In Sierra Leone

Procurement of works, goods and services totaling Le14,168,845,828 were not done according to procurement procedures.

These procurement were done through restrictive bidding method instead of National and International Competitive Bidding methods (NCB & ICB) as required by the Public Procurement Act. The procurement activities were also not advertised.

It was therefore recommended that the PS should do the following; provide documentary evidence to justify the fact that recommendations of the Procurement Officer and the Internal Auditor were not adhered to; provide explanations to justify why the Ministry failed to use the design of the professionals;and provide evidence to justify the fact that the contracts were done through restrictive bidding instead of NCB and ICB.

ALSO READ: Kandeh Yumkella Beats Maada Bio To Meet High Ranking US Lawmakers

The PS said that the third and fourth issue was as a result of an urgent executive directive, for which the Ministry later sought a legal contract document, the concurrence of NPPA as well as approval for payment by the Ministry of Finance and Economic Development.

He noted that the use of the restrictive bidding was approved by the procurement committee and approval was sought from the National Public Procurement Authority (NPPA) to carry out restrictive bidding procedures.

Minutes of the procurement committee and approval from NPPA would be submitted for verification. According to the ICT Manager, AFCOM SL Ltd. was chosen based on quality and location.

ALSO READ: REVEALED: Sacked Ministers May Be Re-appointed By President Koroma

He stated that after feasibility studies, it was discovered that AFCOM had a location, and that they had got similar experience with them. He noted that it was on that basis that (the ICT Unit) recommended AFCOM because of their signal strength.

He also noted that the total service package in terms of Customer care and Technical response is effective. He added that brochure comprised of different packages which suits the Internet requirements of the Ministry of Works, Housing and Infrastructure head quarter.